Crews will be completing the final phase of paving of High School Road Ext. on Wednesday, Oct. 16, and Thursday, Oct. 17.

Weather permitting, the final paving of High School Road Ext. from the roundabout to Main Street and Stevens Street from North Street to Winter Street will be done on Wednesday, Oct. 16, and Thursday, Oct. 17, according to a release from the Barnstable Department of Public Works.

The work will start at 7 a.m. each day and finish by 5 p.m.

The DPW is advising motorists to seek an alternate route during the construction. Periodic delays are expected.